Los Angeles department of building safty logo Permit and Inspection Report banner
6201 W HOLLYWOOD BLVD 90028
APPLICATION / PERMIT NUMBER: 19016-20000-08473
PLAN CHECK / JOB NUMBER: B19VN04674

Plan Check and Permit Information


GROUP: Building
TYPE: Bldg-Alter/Repair
SUB-TYPE: Commercial
PRIMARY USE: (16) Retail
WORK DESCRIPTION: Remove/replace portion of store front glazing, 2 new ladder access mechanical equipment mezzanines, suspended ceiling systetm, new restrooms, concrete ramps/steps and install partition walls for new tenant spaces within ground floor business area. All works are per design
PERMIT ISSUED: Yes PERMIT ISSUE DATE: 06/11/2019 ISSUING OFFICE: Van Nuys
CURRENT STATUS: Permit Finaled CURRENT STATUS DATE: 01/28/2020

Permit Application Status History
Submitted 03/26/2019 APPLICANT
Green Plans Picked Up 04/02/2019 APPLICANT
Assigned to Plan Check Engineer 04/04/2019 ALDOUS CHIC
Disabled Access Plans Picked Up 04/05/2019 APPLICANT
Corrections Issued 04/08/2019 ALDOUS CHIC
Quality Review Completed 04/08/2019 ABDUL CHEGENI
Building Plans Picked Up 04/09/2019 APPLICANT
Applicant returned to address corrections 04/30/2019 ALDOUS CHIC
Applicant returned to address corrections 05/10/2019 ALDOUS CHIC
Applicant returned to address corrections 05/29/2019 ALDOUS CHIC
Plan Check Approved 06/11/2019 ALDOUS CHIC
Issued 06/11/2019 LADBS
Permit Finaled-Status Void 12/18/2019 EDWIN GREGORYONA
Permit Finaled 12/18/2019 EDWIN GREGORYONA
Re-Activate Permit 01/28/2020 EDWIN GREGORYONA

Permit Application Clearance Information
"D" conditions Cleared 04/17/2019 ANNA VAN
"Q" conditions Cleared 04/17/2019 ANNA VAN
"T" removal Cleared 04/17/2019 ANNA VAN
Miscellaneous Cleared 04/17/2019 ANNA VAN
Tract Map conditions Cleared 04/17/2019 ANNA VAN
ZA Case Cleared 04/17/2019 ANNA VAN
Project located in CRA area Cleared 04/19/2019 JIM URQUHART
HPOZ Cleared 04/22/2019 LAMBERT GIESSINGER
Historic monument Cleared 04/22/2019 LAMBERT GIESSINGER
Green Code Cleared 05/24/2019 PARISA ZAHABI
Fire Marshall Fire Life Safety Cleared 05/28/2019 WILLIAM JOHNS
DAS Clearance Cleared 05/31/2019 NORLITO MEDRANO
Eng Process Fee Ord 176,300 Cleared 06/03/2019 JEANETTE VONG

Licensed Professional/Contractor Information
Architect Information
Price,, Jack Dean; Lic. No.: C20327
4011 CRESTHAVEN DRIVE
WESTLAKE VILLAGE, CA  91362
Contractor Information
Corporate Contractors Inc; Lic. No.: 604407-B
2550 CORPORATE PL STE C-111
MONTEREY PARK, CA  91754
Engineer Information
Tanouye,, Russell; Lic. No.: S2850
888 S FIGUEROA ST 18TH FLOOR
LOS ANGELES, CA  90017

Inspection Activity Information

Inspector Information
TIMOTHY POWELL, (213) 482-0360
Office Hours: 7:00-8:00 AM MON-FRI
JONATHAN QUACH, (213) 482-0360
Office Hours: 7:00-8:00 AM MON-FRI
JOHN YAKUBYAN, (213) 482-0360
Office Hours: 7:00-8:00 AM MON-FRI
RONALD JIMENEZ, (213) 482-0360
Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspection Request(s)
  No data available

Inspection Request History
  Light Gage Steel Frame   06/19/2019   Partial Approval   EDWIN GREGORYONA
  Pre-Inspection   06/19/2019   Approved   EDWIN GREGORYONA
  Reinforced Concrete Frame   06/26/2019   Partial Approval   EDWIN GREGORYONA
  Deputy Reinf. Concrete   07/08/2019   Partial Approval   EDWIN GREGORYONA
  Deputy Reinf. Concrete   07/09/2019   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   07/09/2019   Partial Approval   EDWIN GREGORYONA
  Drywall Nailing   07/09/2019   Partial Approval   EDWIN GREGORYONA
  Light Gage Steel Frame   07/09/2019   Partial Approval   EDWIN GREGORYONA
  Deputy Reinf. Concrete   07/10/2019   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   07/10/2019   Partial Approval   EDWIN GREGORYONA
  Deputy Reinf. Concrete   07/11/2019   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   07/11/2019   Partial Approval   EDWIN GREGORYONA
  Deputy Reinf. Concrete   07/12/2019   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   07/12/2019   Partial Approval   EDWIN GREGORYONA
  Drywall Nailing   07/22/2019   Partial Inspection   EDWIN GREGORYONA
  Deputy Drilled-In Anchors   07/23/2019   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   07/23/2019   Partial Approval   EDWIN GREGORYONA
  Deputy Drilled-In Anchors   07/24/2019   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   07/24/2019   Partial Approval   EDWIN GREGORYONA
  Deputy Drilled-In Anchors   07/25/2019   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   07/25/2019   Partial Approval   EDWIN GREGORYONA
  Deputy Drilled-In Anchors   07/26/2019   Conditional Approval   DANIEL MC AULIFFE
  Deputy Steel/Welding   07/26/2019   Conditional Approval   DANIEL MC AULIFFE
  Light Gage Steel Frame   07/31/2019   Partial Inspection   EDWIN GREGORYONA
  Structural Steel Frame   07/31/2019   Partial Inspection   EDWIN GREGORYONA
  Deputy Drilled-In Anchors   08/26/2019   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   08/26/2019   Partial Approval   EDWIN GREGORYONA
  Deputy Drilled-In Anchors   08/27/2019   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   08/27/2019   Partial Approval   EDWIN GREGORYONA
  Deputy Drilled-In Anchors   08/29/2019   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   08/29/2019   Partial Approval   EDWIN GREGORYONA
  Deputy Drilled-In Anchors   08/30/2019   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   08/30/2019   Partial Approval   EDWIN GREGORYONA
  Drywall Nailing   09/06/2019   Approved   EDWIN GREGORYONA
  Deputy Drilled-In Anchors   09/11/2019   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   09/11/2019   Partial Approval   EDWIN GREGORYONA
  Deputy Drilled-In Anchors   09/12/2019   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   09/12/2019   Partial Approval   EDWIN GREGORYONA
  Deputy Drilled-In Anchors   09/13/2019   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   09/13/2019   Partial Approval   EDWIN GREGORYONA
  Deputy Drilled-In Anchors   09/16/2019   Partial Approval   EDWIN GREGORYONA
  Deputy Steel/Welding   09/16/2019   Partial Approval   EDWIN GREGORYONA
  Reinforced Concrete Frame   10/03/2019   Partial Approval   EDWIN GREGORYONA
  Final   11/19/2019   Conditional Approval   EDWIN GREGORYONA
  Green Building Final   11/19/2019   Approved   EDWIN GREGORYONA
  SGSOV-Seismic Gas S/O Valve   11/19/2019   SGSOV Approved   EDWIN GREGORYONA
  Smoke Detectors   11/19/2019   Approved   EDWIN GREGORYONA
  Final   12/18/2019   Permit Finaled   EDWIN GREGORYONA

BACK     NEW SEARCH